Gina Krog

The Gina Krog Field is located in Block 15/5 of the Norwegian Sector in the North Sea.

For the installation of the 12 Anchor Piles for the FSO, MENCK not only provided the MHU 800S Hydraulic Hammer System but also the LMH StabFrame and the CAPE supplied Vibrohammer. The service not only included the provision of all installation equipment from one hand but also on-site project management support to the client project team during project preparation and execution phase. Pile driving started on April 28th, 2016 and the last pile was driven to end penetration on May 20th, 2016.

Documents / LINKS

Videos

  •  
project image
Longditude 58.03
Latitude 2
Market Conventional Oil & Gas
Structure FSO
Hammer MHU 800S
Pile Diameter 2.4 m / 96"
Water Depth 100 m / 328 ft